Westside Plaza – Colorado Springs, CO - Case Study

Details
Two Buildings with Different Hours of Tenant Operation
Replacement of Existing Built-Up Roof System
Economically Installed TPO Roof System
Challenges
Strict noise restriction requirements and tight construction schedules
Tear-down of 24,062 square feet of Built-Up Roof with pea gravel over a wood deck
Solutions
CentiMark offered creative, extended payment terms in consideration of customer’s budget
Flexible construction scheduling facilitated a timely roof installation and noise reduction
Results
Mechanically fastened ½” EPS insulation and 45 Mil TPO roof system
No tenant complaints
Installation completed on-time and within customer’s budget

"The roof was completed on-time without any complaints from the tenants. CentiMark did a great job!"
- P.N. Property Manager – Mountain West Management